Senarai Kontraktor Kerja Utama Bumiputera

No Nama Pakej Tarikh Surat Pemberian Kontrak Kontraktor
PART A - ADVANCE WORKS / ELEVATED
1 AW201
Advance Works Package 1: Design & Build Of Installation, Testing And Commissioning Of TNB Pylon And Overhead Transmission Line Relocation.
23 November 2015 P.E.S.B. Engineering Sdn Bhd
2 AW202
Advance Works Package 2: Design & Build Of Installation, Testing And Commissioning Of TNB Pylon And Overhead Transmission Line Relocation .
23 November 2015 Huls Transmission Sdn Bhd
3 SBPQ
Proposed Design & Build of 17-Storey Police Quarters Consisting of 136 Units Class F Quarters Complete with Facilities and 6-Storey Carpark Podium on Lot 46 and Lot 47, Jalan Suasa 2, Mukim Petaling, Pekan Sungai Besi, Kuala Lumpur for The Development Of The Existing Sungai Besi Police Quarters
15 July 2015 S.N. Akmida Holdings Sdn Bhd
PART B - ADVANCE WORKS / UNDERGROUND
4 JKR CSL
Sign & Build of New JKR Wilayah Persekutuan Workshop Including Automotive and Heavy Machinery Workshop & Associated Buildings at Lot 1571, Jalan 6/19 Cheras Together With “Taska”, Tennis Court & Access Road Development at Existing JKR Wilayah Persekutuan Chan Sow Lin Vicinity.
2 February 2016 Acre Works Sdn Bhd
5 Kraf / C
Design & Build Of New Double Storey Structure For Cafeteria And ‘Preka’ Centre At Craft Complex Kuala Lumpur, Jalan Conlay.
14 March 2016 M.O. Jaya Sdn Bhd
PART C - UNDERGROUND WORKS
6 UNGW
Construction And Completion Of Tunnels, Stations And Associated Structures from Jalan Ipoh North Escape Shaft to Desa Waterpark South Portal
31 March 2016 MMC Gamuda KVMRT (T) Sdn Bhd
PART D - CIVIL & INFRASTRUCTURE / VIADUCT
7 V202
Construction and Completion of Viaduct Guideway and Other Associated Works from Persiaran Dagang to Jinjang.
4 April 2016 Ahmad Zaki Sdn Bhd
8 V210
Construction and Completion of Viaduct Guideway and Other Associated Works From Persiaran APEC to Putrajaya Sentral
19 May 2016 Malaysian Resources Corporation Berhad
PART E - CIVIL & INFRASTRUCTURE / DEPOT WORKS
9 DPT203
Construction and Completion of Earthworks and Other Associated Works for Serdang Depot
5 May 2016 TSR Bina Sdn Bhd
PART F - DESIGNATED SUPPLIER (DS)
10 SBG202
Supply and Delivery of Segmental Box Girders (SBG) (Packages V206 to V210)
25 March 2016 Acre Works Sdn Bhd