SSP Line
Lebuhraya Pintasan Dengkil
Continuation of Lane Closures Along Lebuhraya Pintasan Dengkil FT29, Putrajaya (North bound and South bound)
24 September 2017
23 November 2017
7:00am to 7:00pm & 8:00pm to 6:00am
To facilitate mobilization of machineries, site clearing, soil investigation, piloting, road widening and pier construction for MRT Project

SSP Line
Jalan Kuala Selangor
Continuation of Lane Closures Along Jalan Kuala Selangor (Sungai Buloh bound and Kepong bound)
23 September 2017
22 October 2017
24 hours
To facilitate loading/unloading material and open guard rail, site clearing and tree cutting, mapping and piloting, utilities relocation, temporary works - sheet pile and earth work, soil investigation, road widening and diversion, piling and pile cap, 33kv TNB cable relocation for MRT Construction Works

SBK Line
Cheras Kajang Highway
Partial lane closure on the slip road from Taman Kota Cheras entering the Cheras Kajang Highway (Kuala Lumpur-bound, nearby Station Petronas Batu 9).
18 September 2017
30 September 2017
10:00AM - 4:00PM and between 10:00PM 5:00AM.
To facilitate reinstatement of street lighting, road resurfacing (milling & pavement), permanent signage and road marking works.

SBK Line
Cheras-Kajang Highway
Continuation of slip road closures at Exit 702 and Exit 703 (Kajang-bound and Kuala Lumpur-bound), Cheras-Kajang Highway.
18 September 2017
30 September 2017
10:00PM 5:00AM
To facilitate the maintenance works for Taman Suntex MRT Station and Sri Raya MRT Station, reinstatement of street lighting, reinstatement of permanent signage, road resurfacing (milling & pavement) and road marking works.

SBK Line
Cheras-Kajang Highway (Kajang-Bound)
Continuation of a two -lane closure at the Cheras-Kajang Highway (Kajang-Bound) from
KM 10.6 until KM 11.6 for the stretch of 1KM.
8 September 2017
30 September 2017,
10:00PM - 5:00AM
To facilitate the reinstatement of street lighting, reinstatement of permanent signage and road marking works.

SBK Line
PGA Interchange (Kajang-Bound and Kuala Lumpur-Bound).
Partial lane closure at Exit 701 at the PGA Interchange (Kajang-Bound and Kuala Lumpur-Bound). The closure will be implemented in TWO stages as numbered in the map.

Stage 1, numbered as 1 (18 September 2017 24 September 2017)
- One lane closure on the left-most lane on the slip road entering PGA Kajang Bound and Median 1 lane closure heading towards PGA Bound.

Stage 2, numbered as 2 (25 September 2017 30 September 2017)
- Slip road closure (Kajang Bound) from PGA and Median 1 lane closure heading towards Kuala Lumpur Bound.
18 September 2017
30 September 2017
10:00AM 4:00PM and from 10:00 PM 5:00AM.
To facilitate reinstatement of street lighting, permanent signage and road marking works.

Alternative routes to avoid MRT construction

Description
Type
Download

SBK Line
Alternative routes for Jalan Cheras road closures
General

SBK Line
Alternative routes for Jalan Semantan to Kota Damansara road closures
General

SBK Line
Alternative For Lebuhraya Damansara-Puchong (LDP), Jalan Damansara
General

SBK Line
ALTERNATE ROUTE JALAN DAMANSARA
General

SBK Line
ROADS DURING CONSTRUCTION- NORTHERN
General

SBK Line
ROADS DURING CONSTRUCTION- CITY CENTER
General